Bus Garage Status



Status of the Bus Garage Project


On November 5, voters approved the bus garage project for a max of 2.985 million. 

We are currently working with ICON Architects to put together the bid specs for a public bid. We are meeting on Nov. 8 to go through and solidify timelines for the bid spec, release of bids, bid window, and projected date for opening bids. More information to follow. 




Click here for Additional Information on the Operating Referendum and Ag Land Tax Credit


Calculate the estimated impact of the referendum on your property taxes!

Calculator.pngTax Impact Calculator



 

Virtual Bus Garage Tour-Click Here!

Project Timeline:

Architect Meeting- Nov. 8
Bid Spec Development-Dec. 2019
Bid Spec Release-Jan. 2020
Bid Window-Jan./Feb. 2020
Projected Bid Opening-Feb. 2020
Projected Start of Construction-Apr./May 2020
Projected Completion of Construction-Nov. 2020